电力花园(二期)                                                                       混凝土角撑拆除方案
目   录
第一章  编制依据及说明 ······················································································ 1
1.1  编制依据 ·············································································································· 1 1.2  编制说明 ·············································································································· 1
第二章  工程概况 ······························································································· 1
2.1  工程总体概况 ········································································································ 1 2.2  分项工程概况 ········································································································ 1
第三章  角撑拆除方案 ························································································· 2 第四章  施工工艺 ······························································································· 2
4.1  工艺流程 ·············································································································· 2 4.2  工艺措施 ·············································································································· 2
4.2.1  拆撑平台搭设 ······························································································· 2 4.2.2  混凝土角撑拆除 ···························································································· 2 4.2.3  成品保护措施 ······························································································· 3
第五章  注意事项 ······························································································· 3
5.1  监测加密措施 ········································································································ 3 5.2  安全保证措施 ········································································································ 3
中国建筑第五工程局有限公司                                                                               1
电力花园(二期)                                                                       混凝土角撑拆除方案
第一章  编制依据及说明
1.1  编制依据
1、《混凝土结构工程施工质量验收规范》(2011年版),GB50204-2002; 2、《建筑施工安全检查标准》,JGJ59-2011;
3、《建筑施工扣件式钢管脚手架安全技术规范》,JGJ130-2011; 4、《建筑施工模板安全技术规范》,JGJ162-2008;
5、电力花园二期基坑支护设计图,中国京冶工程技术有限公司;
6、电力花园二期建筑、结构设计图,深圳市建筑设计研究总院有限公司。
1.2  编制说明
本工程基坑局部设计有混凝土角撑支护,混凝土角撑处于主体结构投影范围之内,后期需进行拆除,特编制本方案,适用于电力花园(二期)工程混凝土角撑拆除施工。
第二章  工程概况
2.1  工程总体概况
电力花园(二期)工程位于深圳市南山区后海大道与创业路交汇处东南角,创业路以南,后海大道以东。本工程占地面积约19944.46m²,建筑面积约90932.26m2,其中地上约57601.56 m²,地下约33330.8 m²,共有住宅545户。
地上住宅及商住楼共5栋:3#楼27层,高83.6m;4#楼27层,高83.6m;5#楼A座22层,高66.4m;5#楼B座27层,高87.8m;6#楼30层,高96.0m。地下室为两层车库,地下一层与一期地下室连通。
建设单位:深圳妈湾电力有限公司
设计单位:深圳市建筑设计研究总院有限公司 施工单位:中国建筑第五工程局有限公司 勘察单位:深圳地质建设工程公司 监理单位:中海监理有限公司
2.2  分项工程概况
本工程基坑支护东南角4-4剖面、西南角8-8剖面、西北角10-10剖面、北侧14-14剖面为混凝土角撑支护方式。根据设计图纸,混凝土角撑为上下两道:上部第一道角撑截面尺寸
中国建筑第五工程局有限公司                                                                               1
电力花园(二期)                                                                       混凝土角撑拆除方案
为800mm×800mm,角撑面标高为-1.000m;下部第二道角撑截面尺寸为1000mm×1000mm,角撑面标高为-4.000m。
根据地下室结构图纸,两道混凝土角撑均处于负一层结构内,且第一道角撑与地下室顶板结构有部分交叉。因此,在支护角撑部位,必须先将角撑破除,才能施工地下室负一层结构。
第三章  角撑拆除方案
根据设计要求及现场条件,本工程混凝土角撑拆除采用搭设支撑架体,再人工使用风镐破除的方式拆除混凝土角撑。
第四章  施工工艺
4.1  工艺流程
角撑部位负二层结构及外墙防水完成后,外墙回填C15素混凝土至-7.000m标高→在混凝土角撑处搭设拆撑支架,做好防护措施→人工施工风镐拆除角撑
4.2  工艺措施
4.2.1  拆撑平台搭设
1、在准备凿除的支撑下采用φ48×3.5钢管搭设操作平台,第一道角撑拆撑平台搭设高度为3.9m,第二道角撑拆撑平台搭设高度为0.7m。
2、拆撑平台立杆纵横向间距为600mm,距地200mm高度设置一道扫地杆,扫地杆向上每步水平杆间距为1500mm。
3、钢管立杆顶部采用顶托上托双钢管,双钢管上铺木枋模板顶至混凝土角撑底面,木枋间距300mm。
4、拆撑平台周围设置1.5m高防护栏杆,栏杆外满挂密目安全网。
5、拆撑平台搭设在负一层板面上,在架体立杆下垫废旧模板,并沿脚手架的长度方向每隔3m设置一道横向剪刀撑,以确保脚手架底部均匀受力及稳定性。
6、架体下铺设多层麻袋,防止支撑拆除时对结构的损伤。
4.2.2  混凝土角撑拆除
1、拆撑平台搭设完成后,采用风镐对混凝土支撑进行打凿。
中国建筑第五工程局有限公司                                                                               2
电力花园(二期)                                                                       混凝土角撑拆除方案
2、打凿时,先破除角撑混凝土,从上往下,从面往里;凿除混凝土过程中,不能割断角撑主筋。
3、待角撑混凝土基本剔除完后,再割除角撑主筋;角撑主筋割除应从上往下,从中间往两端进行。
4、混凝土角撑打凿后的废渣应随打随清。拆除一定区域后,采用人工和小型机械将碎块归堆,用钢丝网兜和吊斗装好,在夜间配合塔吊吊运至基坑外侧,装车外运,对废钢筋、格构柱用切割机具切割成小段外运。白天混凝土支撑凿好后,晚上要及时清理,吊运采用塔吊。
4.2.3  成品保护措施
每道支撑拆除时,底板或楼板已经浇筑完成,墙、柱、楼梯插筋基本到位,在拆除过程中,应对底板面层、墙柱楼梯插筋进行保护,具体措施如下:
1、板面层:在底板面层铺设竹笆(麻袋),支撑破处混凝土块直径不大于300,尽量不对底板面层形成冲击。
2、插筋:部分墙柱楼梯插筋位于支撑位置,在支撑拆除过程中,控制破处混凝土块体积大小,对个别部位钢筋插筋采取钢管配套模板防护隔离,防止混凝土块将钢筋压弯。柱、墙等插筋上部有直螺纹连接的丝牙,必须加强保护,采用直螺纹套筒进行保护,将相应规格直螺纹套筒拧在墙、柱插筋上,(不宜过紧)防止支撑拆除过程中掉落的混凝土对丝牙造成破坏,在支撑拆除完成后,拧下该套筒,清理丝牙,再施工上部钢筋。
3、后浇带:后浇带采取模板封闭密实,严防混凝土碎片进入后浇带内。
第五章  注意事项
5.1  监测加密措施
在支撑拆除期间对基坑周围管线水平位移、沉降、地下水位状况进行加密监测,出现异常及时通知监理、设计、业主及施工单位,及时进行处理。
5.2  安全保证措施
1、架子工应持证上岗;
2、拆撑平台安装时,应两人配合搭设;
3、平台上的混凝土渣应及时清理,不得堆放过多;
4、进场施工机械必须要进行验收,机械使用期间由专门负责人进行维修保养; 5、专职电工值班制度,操作过程中派专人巡视;
中国建筑第五工程局有限公司                                                                               3
电力花园(二期)                                                                       混凝土角撑拆除方案
6、搭拆脚手架时,施工现场必须有专人指挥,拉设警戒线,禁止非作业人员进入作业区; 7、施工时候,必须严格控制脚手架上的施工荷载; 8、遇恶劣天气影响施工安全时,不得进行脚手架施工; 9、夜间施工,必须保证有足够的照明。
中国建筑第五工程局有限公司                                                                               4