您的当前位置:首页冲击碾压数据

冲击碾压数据

来源:九壹网
冲击压路机碾压数据

施工单位:旅游产业大道东段新建工程第三标段 监理单位:北京众鑫伟业监理有限公司 桩号K12+500K12+520K12+540K12+560K12+580K12+600平均沉降说明:

冲击碾压前高程左 距中6m103.458102.779102.096101.38100.67499.983中桩103.546102.835102.196101.446100.722100.041冲击20遍高程中桩103.455102.821102.12101.346100.66999.9530.086右 距中6m左 距中6m103.503102.796102.108101.329100.6299.0.0770.0840.1170.0590.1020.111右 距中6m左 距中6m103.611102.915102.15101.432100.72199.99103.381102.695101.979101.321100.57299.8721、梅花冲击碾 型号: YCT252、冲击速度:15km/h

测量: 计算: 监理:

冲击压路机碾压数据

施工单位:旅游产业大道东段新建工程第三标段 监理单位:北京众鑫伟业监理有限公司 桩号K12+500K12+520K12+540K12+560K12+580K12+600平均沉降说明:冲击碾压前高程左 距中6m103.458102.779102.096101.38100.67499.983中桩103.546102.835102.196101.446100.722100.041冲击5遍高程中桩103.487102.793102.218101.41100.655100.041右 距中6m左 距中6m103.546102.885102.078101.374100.70299.9760.0410.0790.0220.0840.0730.068右 距中6m左 距中6m103.611102.915102.15101.432100.72199.99103.417102.7102.074101.296100.60199.9150.0451、梅花冲击碾 型号: YCT252、冲击速度:15km/h

测量: 计算: 监理:

冲击压路机碾压数据

施工单位:旅游产业大道东段新建工程第三标段 监理单位:北京众鑫伟业监理有限公司 桩号K12+500K12+520K12+540K12+560K12+580K12+600平均沉降说明:冲击5遍高程左 距中6m103.417102.7102.074101.296100.60199.915中桩103.487102.793102.218101.41100.655100.041冲击10遍高程中桩103.472102.875102.137101.377100.68699.97右 距中6m左 距中6m103.52102.813102.125101.346100.63799.9070.019-0.0120.078-0.0420.0120.026右 距中6m左 距中6m103.546102.885102.078101.374100.70299.976103.398102.712101.996101.338100.599.80.0211、梅花冲击碾 型号: YCT252、冲击速度:15km/h

测量: 计算: 监理:

冲击压路机碾压数据

施工单位:旅游产业大道东段新建工程第三标段 监理单位:北京众鑫伟业监理有限公司 桩号K12+500K12+520K12+540K12+560K12+580K12+600平均沉降说明:冲击10遍高程左 距中6m103.398102.712101.996101.338100.599.8中桩103.472102.875102.137101.377100.68699.97冲击15遍高程中桩103.453102.824102.136101.356100.699.963右 距中6m左 距中6m103.507102.798102.108101.327100.619.8830.051-0.0610.0210.020.0530.022右 距中6m左 距中6m103.52102.813102.125101.346100.63799.907103.347102.773101.975101.318100.53699.8670.0171、梅花冲击碾 型号: YCT252、冲击速度:15km/h

测量: 计算: 监理:

冲击压路机碾压数据

施工单位:旅游产业大道东段新建工程第三标段 监理单位:北京众鑫伟业监理有限公司 桩号K12+500K12+520K12+540K12+560K12+580K12+600平均沉降说明:冲击15遍高程左 距中6m103.347102.773101.975101.318100.53699.867中桩103.453102.824102.136101.356100.699.963冲击20遍高程中桩103.455102.821102.12101.346100.66999.9530.003右 距中6m左 距中6m103.503102.796102.108101.329100.6299.-0.0340.078-0.004-0.003-0.036-0.005右 距中6m左 距中6m103.507102.798102.108101.327100.619.883103.381102.695101.979101.321100.57299.8721、梅花冲击碾 型号: YCT252、冲击速度:15km/h

测量: 计算: 监理:

公司 时间:2012.04.16高差中桩0.0910.0140.0760.10.0530.088右 距中6m0.1080.1190.0420.1030.1010.1平均值0.0920.0720.0780.0870.0850.100公司 时间:2012.04.16高差中桩0.0590.042-0.0220.0360.0670右 距中6m0.0650.030.0720.0580.0190.014平均值0.0550.0500.0240.0590.0530.027公司 时间:2012.04.16高差中桩0.015-0.0820.0810.033-0.0310.071右 距中6m0.0260.072-0.0470.0280.0650.069平均值0.020-0.0070.0370.0060.0150.055公司 时间:2012.04.16高差中桩0.0190.0510.0010.021-0.0030.007右 距中6m0.0130.0150.0170.0190.0190.024平均值0.0280.0020.0130.0200.0230.018公司 时间:2012.04.16高差中桩-0.0020.0030.0160.010.020.01右 距中6m0.0040.0020-0.002-0.002-0.007平均值-0.0110.0280.0040.002-0.006-0.001